TIMELINE TO EXCELLENCE

Phase 1

 

 
View Reactor Example
bullet image Environmental and Geotech studies completed November 2006
bullet image Plant approved February 1, 2007
bullet image Construction starts February 2007
bullet image Concrete Foundation work complete by July 2007
bullet image Utility distribution and property access completed July 2007
bullet image Tank Storage installed and complete October 2007
bullet image Reactor 1 and associated equipment 1st Quarter 2008
bullet image Reactor 2 and associated equipment 1st Quarter 2008
bullet image Reactor 3 and associated equipment 1st Quarter 2008
bullet image Projected Capacity: 90kt Annually
 
View Plant Layout


Phase 2

 

bullet image Reactor 4 and associated equipment End of Year 2009
bullet image Reactor 5 and associated equipment 2009
bullet image Reactor 6 and associated equipment 2009
bullet image Projected Capacity: 135kt Annually
 
View Future Plant Layout

 


Capacity Reservations Available